Missouri Community College Foundation Settlement Repair
Sedalia, Missouri
The Challenge
Voids and settlement issues impacted a total area of 3,660 ft.
The Solution
Fill the subsurface voids beneath the Hopkins building with Groundworks polyurethane injection.
The Impact
Filled voids and raised settled slab in just two days with minimal disruption for the building’s occupants.
The Challenge
Voids and settlement issues impacted a total area of 3,660 ft.
Located in Sedalia, Missouri, State Fair Community College (SFCC) is a public, nonprofit college that serves the educational needs of more than 5,000 students each year from 14 counties in west central Missouri. The William C. Hopkins Student Services Building located on campus started showing visible signs of foundation settlement. The building, which opened in 1987, is a vital part of the everyday operations of the college. Therefore, SFCC brought in Terracon Consultants, Inc. to assess the movements in the upper level floor of the Hopkins building and provide recommendations.
Terracon used ground-penetrating radar (GPR) to perform an upper-profile geophysical survey. Results showed multiple voids underneath grade-supported floor slabs that had already settled several inches. Voids and settlement issues impacted a total area of 3,660 ft along the north exterior wall of the building. Although the building structure was still technically safe for occupancy, the trend was apparent and repair options for the foundation settlement were requested by the college.
Key Facts
5,000
Students
2 Days
Installation Time
Minimal
Disruption
3,660 Ft
Total Impact Area
The Solution
Fill the subsurface voids beneath the Hopkins building with polyurethane injection.
Terracon provided two options for SFCC. Option 1 involved the complete removal and replacement of grade-supported floor slabs. This would be very expensive and would involve major disruption of the building’s everyday functionality. Interior partition walls and under-slab HVAC and utilities would be involved, and all functions in at least the north half of the building would have to be relocated. At some points, the work would likely require the entire building to be vacated. Worst of all, only a loose estimate of total project time could be provided as there were so many variables. Option 2 involved restoration of the floor slab support by injecting expandable polyurethane resin to raise the slab, fill the voids, and stabilize the soil beneath the building.
Option 2 was the only feasible choice for SFCC. In their final report, Terracon stated that Groundworks had provided services on a similar Terracon project in the past (a health care facility), and that Groundworks’ product and process had delivered the results required in that case. SFCC chose Groundworks to fill the subsurface voids beneath the Hopkins building, raise the settled foundation, and stabilize the base and sub-base soils below with polyurethane injections.
The Impact
Filled voids and raised settled slab in just two days.
Groundworks technicians arrived on the scene, began work, and finished the job in just two days with minimal disruption for the building’s occupants. During the repairs, normal building activities continued, and there was no disruption to HVAC or utility services. Polyurethane injections quickly and effectively filled the identified voids below the building and raised the settled slab back to a level condition.
Trusted by Industry Leaders Nationwide
Leading brands across government, commercial, and industrial sectors choose Groundworks for their most challenging projects.





