Telogia Power Plant Truck Tipper Stabilization

image of Telogia truck tripper with truck on it
The Challenge

The Telogia Power Plant truck tipper foundation was settling and the columns were out of plumb.

The Solution

Groundworks installed 6 push piers to support the truck tipper foundation.

The Impact

The truck tipper foundation was stabilized and the project was completed within the single day time-frame requested by the company.

MapPin Icon Location: Telogia, Florida

House Icon Project Type: Industrial


The Challenge

The foundation of the Telogia truck tipper was settling.

The foundations and supporting columns of the Telogia Power Plant’s truck tipper began to shift and settle. Semi-trucks loaded with wood chips would back onto the tipper, where they were hydraulically raised at an angle to unload the trailers.

The truck tipper was supported by concrete foundations beneath its hydraulic and hinge components. Over time, the repeated loading caused these foundations to settle in opposite directions, resulting in the supporting columns moving 3 to 4 inches out of plumb. This movement also created a 7-inch gap between the ramp and approach slab.

As the foundations continued to settle, the supporting columns were unintentionally rotating farther out of alignment, increasing concerns that continued movement could eventually cause the columns to tip. With as many as one truckload arriving every 30 minutes, the facility needed a solution that could stabilize the foundations while minimizing disruption to operations.

Key Facts

7 Inch

Gap Between Ramp and Approach Slab

1 Day

Installation Time

Minimal

Operational Interruption

6

Push Piers


image of gap between approach slab and truck tipper foundation before repair from Groundworks
The Solution

Push piers were installed to properly support the tipper.

Scheduling was critical because truck traffic had to be temporarily stopped during the repair. Groundworks was given a 24-hour window to complete the installation and bring the columns as close to plumb as possible.

Six push piers were installed at each foundation to an approximate depth of 40 feet. Soil reports identified a shallow layer of very loose material, so the piers were advanced through the weaker soils to provide support at greater depths. Four piers were installed along the outside edges and two along the inside edges of each foundation.

Once installed, the push pier system was used to lift and reposition the foundations, bringing the supporting columns closer to their original alignment.


The Impact

The project was completed quickly with minimal operational interruption.

Groundworks successfully lifted and stabilized the foundations, bringing the supporting columns closer to plumb and closing the 7-inch gap between the ramp and approach slab.

The entire repair was completed within the required 24-hour window, allowing truck traffic to resume and the facility to return the tipper to operation.