Skip to Main Content

County of Santa Cruz Culvert Rehabilitation

Santa Cruz, California

Culvert Rehabilitation Polyurethane Injection Santa Cruz California
The Challenge

Significant voids and weakened support soils around the CMP culvert.

The Solution

Polyurethane was used to fill annular voids and densify weak soils outside of the culvert.

The Impact

Culverts and roadway structures stabilized in two weeks.

MapPin Icon Location: Santa Cruz, CA

House Icon Project Type: Public Works

Wrench Tool Icon Repair Type:  Infrastructure Rehab


The Challenge

Emergency repair and washout prevention.

The County of Santa Cruz California was experiencing a common issue, degraded stormwater conveyance infrastructure that needed rehabilitation. The County was evaluating the potential for relining some of their Corrugated Metal Pipe using a cementitious lining application from CentriPipe. During a site visit, the CentriPipe representative Donald Sims noted the presence of significant voids and weakened support soils around the CMP and recommended Groundworks’ polyurethane injection application as a solution.

Key Facts

218 Ft

Culvert Stabilized

2 weeks

Installation Time

0

Traffic Interruption

>20 Ft

Voids Filled


The Solution

20 ft voids filled with a highly dense soil polymer matrix.

The Capitola Rd Pipe is a 66-inch diameter, 55-foot long, badly deteriorated Corrugated Metal Pipe (CMP) culvert that showed signs of settlement and structural damage. The voids were found to be extensive, nearly 20 ft across and 20ft deep toward the surface and required void-filling and densification in order to support the culvert, roadway, parking lane, and sidewalk. To do this, Groundworks injected its proprietary two-part, hydro-insensitive polyurethane through the culvert and into the void area. 

This geotechnical polyurethane is designed to have optimal spread and cure time, making it ideal for a combined void-filling and soil-stabilization product. Once injected, the polyurethane initially spreads in a liquid form and progressively expands throughout the void area and adjacent soils to create a highly dense soil polymer matrix.

A second area that required help was a 84-inch, 163-foot long CMP culvert that ran underneath the intersection of Sumner Rd and Dolphin Drive in the City of Aptos. While not as deteriorated as the Capitola Rd section, the pipe envelope was deteriorating which resulted in water infiltration and soil subsidence which ultimately led to a sinkhole effect resulting in considerable pavement settlement.


The Impact

Culverts and roadway structures stabilized in 2 weeks.

In both culverts, the initial approach was to stabilize the invert using a special high-density mortar from CentriPipe. Afterward, Groundworks made injections from the interior of the pipes and stabilized the annular voids. With the Capitola Rd Culvert, the focus was on the upstream end of the pipe to combat against the encroaching storm season, with the longer downstream section being addressed later. With the Sumner Rd Culvert, the pipe was stabilized throughout, and Groundworks additionally performed injections on the surface to stabilize the pavement and realign the roadway. After the injections the pipes were then relined using the CentriPipe Cementitious lining system.

The project was performed under emergency contract and required minor water bypass with no impact outside the pipe, and all access for tools, piping, etc. had to be via a direct access manhole. The project was completed in 2 weeks and the soil contact was re-established with the culverts and roadway structures. The repair was just in time, as almost immediately after the project was completed the County experienced substantial rainfall which could have been disastrous to both roadways.


Trusted by Industry Leaders Nationwide

Leading brands across government, commercial, and industrial sectors choose Groundworks for their most challenging projects.


Ready to Solve Your Project’s Toughest Challenges?

More Government Case Studies