Stormwater Drainage Channel Repair

San Bernardino, CA

The Challenge

A 150-foot section of the County’s drainage channel developed voids, leading to water flow issues and settlement.

The Solution

Injection tubes were strategically placed to fill voids and stabilize both the lower and upper sections of the drainage structure.

The Impact

The strategic injection placement reinforced the drainage structure, preventing further erosion and structural damage.

MapPin Icon Location: San Bernardino, CA

House Icon Project Type: Public Works

Wrench Tool Icon Repair Type: Void Filling


The Challenge

150-linear-foot Drainage Channel developed Voids

A 150-linear-foot section of the drainage channel had developed voids beneath the concrete panels, causing significant water flow beneath the panels instead of over them during rain events. This situation led to settlement in parts of the structure, further compromising its stability. The County sought a cost-effective solution to extend the life of the drainage system and avoid the high costs associated with a full rip-and-replacement project, looking for a more efficient method to address the underlying issues without disrupting the overall infrastructure.

Key Facts

150 Linear Ft

Drainage Channel

Avoided

Rip and Replace

$ Millions

Saved

4 Ft

Injection Grid


The Solution

4-Foot grid of injections tubes placed.

Injection tubes were placed on a 4-foot grid along the bottom of the drainage structure and halfway up the side walls to address existing voids. This strategic placement ensured that both the lower and upper sections of the structure were effectively stabilized, improving the overall integrity of the drainage system. The targeted injections filled the voids and reinforced the structure, helping to prevent further erosion and settlement.


The Impact

Enhanced stability and prevented erosion in drainage structure.

In order to stabilize the drainage structure, injections were strategically placed on a 4-foot grid along the bottom and halfway up the side walls. This approach ensured comprehensive coverage and effective void filling, helping to prevent further erosion and structural damage​

County Channel Repair

Trusted by Industry Leaders Nationwide

Leading brands across government, commercial, and industrial sectors choose Groundworks for their most challenging projects.


Ready to Solve Your Project’s Toughest Challenges?

More Government Case Studies