Twin Warehouse Foundation Repair
Roscoe & Andover, South Dakota
The Challenge
Two identical grain storage buildings in South Dakota were experiencing concrete foundation settlement.
The Solution
The Polyurethane injection process was used to lift and stabilize the storage facilities.
The Impact
Stabilized, lifted, and returned to service 28,800 square feet of storage facility in a matter of a few days at each site.
Location: Roscoe, SD & Andover, SD
Project Type: Warehouses
Repair Type: Tilt-Up Building Stabilization
The Challenge
Buildings experiencing concrete foundation settlement.
Two identical grain storage buildings in South Dakota (one in Roscoe, the other in Andover) were experiencing concrete foundation settlement. The buildings each store 1.5 million bushels of grain, are 600 feet long by 135 feet wide, and feature a series of tunnels beneath them to assist with grain conveyance and to provide ventilation. The foundation slabs for both buildings were eight-inch reinforced 3,000 psi concrete. Groundworks was contacted to help level the concrete foundations and stabilize the underlying soils, with a focus at each building on a 12-foot by 600-foot section on either side of an aeration tunnel that had settled and cracked.
During the first 18 months of service, the Roscoe warehouse averaged 1.5 inches of foundation settlement, while the Andover warehouse averaged 0.75 inches. The maximum settlement observed was three inches at the Roscoe location. Soil testing showed no specific soil anomalies at depth at either site. However, drilling revealed that soils at the Roscoe location were highly saturated while Andover’s soil moisture content was only slightly above normal. It was learned that during construction of the facilities, both locations experienced a major rain event and an accumulation of snow prior to installation of the roof systems. The runoff from both events likely seeped through the joints where the tunnels and slabs met causing erosion along the exterior of the tunnels and saturating the subsoils.
Key Facts
28,800 Sq Ft
Storage Facility
5 Days
Installation Time Per Site
3,000 Sq Ft
Foundation Lifting Per Day
¾ – 1½ Inches
Foundation Settlement
The Solution
Polyurethane injection process was used to lift and stabilize the storage facilities.
The Polyurethane injection process was a natural fit to lift and stabilize the storage facilities because of its hydro-insensitive properties and high weight-bearing capacity. Because both facilities run year-round, repairs had to be made quickly during a scheduled outage window. Groundworks crews rose to the challenge. The team averaged over 2,000 square feet of Polyurethane injection foundation lifting per day at the Roscoe location and approximately 3,000 square feet per day at Andover. At Roscoe, soybeans were stored in one half of the facility while the crew was on site. Once one side of the floor was lifted, the beans were transferred to the completed area so that work could continue on the other half of the floor. At Andover, all repairs were completed in just five days and the client began restocking the storage facility within three hours of Groundworks’ departure. Both facilities were back online immediately after the work was completed.
The Impact
Stabilized, lifted, and returned to service 28,800 sq ft of storage facility.
Groundworks stabilized, lifted, and returned to service 28,800 square feet of storage facility in a matter of a few days at each site, exceeding the customer’s need for speed and efficiency. Groundworks’ zero-excavation concrete leveling solution allowed the grain storage facility to quickly and effectively repair the settlement problem, restore original design capability, and greatly reduce production downtime. The facility is now better able to accommodate high-volume grain loads without any hesitation.
Trusted by Industry Leaders Nationwide
Leading brands across government, commercial, and industrial sectors choose Groundworks for their most challenging projects.





