Caltrans Ferry Dock Emergency Void Repair in Rio Vista, CA

The Challenge

Wildlife activity undermined the ferry dock slab, creating voids up to 1 foot deep and prompting early repairs to prevent service interruptions.

The Solution

Polymer was used to stabilize the slab by injecting structural polyurethane into drilled voids for soil compaction and support.

The Impact

The dock was stabilized in three shifts, restoring service in one day and regaining full structural capacity.

MapPin Icon Location: Rio Vista, CA

House Icon Project Type: Transportation

Wrench Tool Icon Repair Type: Void Filling


The Challenge

Voids throughout a 44′ x 24′ portion of Ferry Dock.

The ferry dock slab was severely compromised due to wildlife activity, which caused significant voids to form beneath its structure. These voids, measuring between 6 inches to 1 foot across the entire 44-foot by 24-foot slab, posed a serious structural concern. As a result, ferry dry dock maintenance was scheduled earlier than usual to address the issue promptly and prevent further damage. The situation carried a high potential for service interruptions, necessitating immediate and effective repairs to ensure continued operations.

Key Facts

44′ x 24′

Void Range

1 Day

Installation Time

3-Shifts

Ferry Downtime

½ – 1 Ft

Polyurethane Injection Depth


Caltrans Ferry Dock Repair
The Solution

½ – 1 Ft rods and polymer were used to fill the voids.

To remediate the slab and address the void areas, Polymer was utilized as the primary solution. The process began by drilling 1/2-inch holes at designated injection points and inserting 1/2-inch rods to the appropriate depth. Once prepared, structural polyurethane was injected to compact the underlying soil, fill the voids, and stabilize the slab’s support structure effectively.


The Impact

Ferry Dock stabilized in 1 day, impacting only 3 shifts.

The dock was successfully stabilized in just three shifts, minimizing downtime and restoring service within a single day. All voids throughout the slab were addressed, ensuring the structure regained its required weight-bearing capacity and overall stability. This work was carefully coordinated with the drydock schedule to ensure seamless integration with ongoing operations.


Trusted by Industry Leaders Nationwide

Leading brands across government, commercial, and industrial sectors choose Groundworks for their most challenging projects.


Ready to Solve Your Project’s Toughest Challenges?

More Void Fill Case Studies